Project Report : Surrey Office
John Meldrum, Office Manager (Surrey)

Tulsa Events Center
From my last report in our August Details, this project is now complete.
Thanks to Schuff Steel, Mid-West, for the opportunity to work on this special project.
Genenetch Building 50
As of this report, all of the issues which kept this project on hold will finally be completed and the drawings all shop issued.
Berlin N. H. Federal Correctional Institute
As of my last notes the detailing on this building was complete. However, we received a few last minute revisions, so we are now putting on the last touches.
Maritza Power Plant Unit #2 – Boiler House
We have concluded our portion of the work on this project with all being shop issued.
Alstom - RDK8 Project
This Boiler Building is estimated to be approximately 8250 M. Tonnes, with 36 individual levels of platform steel. The structure rises 118.500 metres. We are charged with the production of shop and erection drawings, and also the partial connection design, for which we are presently working with SCI.
Drawings and connection design information is to be provided in English and German.
Hugh Dobbie and myself attended a kick-off-meeting in Alstom’s office in Stuttgart, Germany, where we had the opportunity to meet some of the key personnel.
I would like to take this time to thank our clients and our staff over this holiday period, and wish every one a prosperous and fulfilling New Year.